Page 16 - July-Aug2020 Vol38 No2
P. 16

5G and Small Cell from page 15                 Given the number of field contractors      issued permits. Not all the permitted
                                             and subcontractors installing the fiber      sites go under construction when the
installation can have a much larger impact   both underground and overhead, many          permit is issued. Problems still exist
on the city than the actual installation of  of the general requirements contained        regarding getting notifications as to when
the small cell equipment. Additionally,      in the issued permits were developed         construction begins and is completed.
the fees charged by the cities for           “on the fly.” In order to minimize the
fiber installation are not subject to        impact on the motoring public and              For that reason, an eight-week time
the regulations placed on small cell         businesses, construction is limited to the   limit was placed on the permits. If the
installations by the Act.                    hours of 9 a.m. to 3 p.m.                    contractor does not complete the project
                                                                                          or request a valid time extension within
  The City of Memphis has a robust             The name of the contractor must be         that period, the permit is voided, and a
operation for permitting and monitoring      on each piece of equipment working           new permit must be applied for. 
the installation of fiber optic cable. To    within the ROW, so that any issues
date, Memphis has permitted the              arising from the construction can be          Balancing the Challenges With Increased
installation of more than 372 miles of       reported by name. In addition to all the     5G Speed
fiber within the City ROW (beginning in      typical utility location requirements (via
October 2017). It is not uncommon for        811), the contractors also are required to     The small cell program is happening. It
14 to 16 permits to be issued in a single    notify the Memphis Signal Maintenance        is real and it will last for a long time. With
day. The size of the permits varies from a   Office if constructing within 350 feet of a  small cells coming, major fiber installation
few feet to more than a mile or two.         signalized intersection.                     will follow. It is almost like a right hook
Labor-Intensive Permitting Process                                                        followed by a left upper cut. 
                                               In some instances, such as
  Issuing and tracking this volume           installing fiber in the downtown                In summary, if you are a municipality
of permit requests is labor inten-           area, a special permit may be applied        that hasn’t experienced the thrill of 5G yet,
sive. The city has a consultant assigned     to allow installation after hours,           you will.  In your positions, you already
to receive the permit requests, track the    or on Saturdays. This is mainly to           are accustomed to dealing with elected
payments, review the permits, and issue      avoid peak traffic hours and allow           officials, neighborhood organizations, and
permit approvals. In addition, other con-    the workers to complete the fiber            angry citizens. You won’t be disappointed.
sultants work on installations taking place  installation as soon as possible and exit
throughout the city. The fees paid by the    the area.                                      With many of the concerns, demands,
installers more than cover the cost of the                                                threats, etc., that come to your office
necessary additional personnel.                Notification of construction has           regarding the small cell program, your
                                             been a challenge, due to the number of       hands are tied.  You can always say “the
                                                                                          state legislature made me do it.

16	 TPW July/August 2020
   11   12   13   14   15   16   17   18   19   20   21