Page 7 - July-Aug22Vol40No2
P. 7

a competitive process to select an   Pumps are a specialized design, and   chose to use the new HEC-RAS 6.0 2D
         engineering consultant,” WTRBA      pumping at a larger scale requires a   modeling software for a more accurate
         Executive Director David Blackwood said,   thorough team.”               representation of the discharge from this
         “so [WTRBA] solicited proposals through   The new system would soon offer   flat drainage basin.” 
         a public process to evaluate the skills and   Tiptonville the ability to operate   The team planned to install multiple
         capabilities of interested consultants. It is   flood control automatically, providing   large pumps, three-phase electricity, and
         always important that the most qualified   immediate response to stormwater events   enclosed facilities for the pump stations.  
         proposal is selected to execute a project.”   with no need of volunteer labor from
           Barge Design Solutions, Inc. (Barge)   local farmers and their tractor pump. At   Optimizing the Design
         joined the competitive pursuit based on   last, a permanent solution for overcoming   Although the challenge of funding
         the design team’s specialized experience   flooding in the Tiptonville area was in the   was out of the way, the team still faced a
         with stormwater pump station design,   works.                            major hurdle in planning: how to develop
         flood plain modeling, benefit-cost analysis,                             an accurate inflow hydrograph from
         and working knowledge of the proposed   Initial Planning Gets Underway    the upstream drainage area to optimize
         Tennessee project sites.              Once funding and a notice to proceed   the design for the community’s flood
           “Our team has a history of supporting   were in place, Barge’s design team began   mitigation system. 
         West Tennessee, so pursuing the     the important process of securing permits   “Accurate discharge estimates are critical
         Tiptonville project was an effort we   related to impacts to the adjacent levee and   in determining sizing of the large pump
         believed in doing as a service to the   stream. Coordination with the Tennessee   station,” Barge Project Engineer Clayton
         community,” Barge Vice President and   Department of Environment and     Foster said. “Given the flat topography
         Senior Project Manager Trevor Cropp said.   Conservation (TDEC) and the US Army   of the land, even a small miscalculation
         “Our knowledge of West Tennessee and the   Corps of Engineers (USACE) was critical.   in stormwater inflow could result in an
         team’s in-house capabilities put us in a solid   Barge identified utilities and   excessive increase in inundation area,
         position to effectively complete the project   infrastructure that would be required   flooding residential homes.”  
         from start to finish.”              to support the site’s new pump station.   Traditional hydrology methods were first
           Three NDRC Grant projects were    Since the watershed was flat, the team   used and resulted in a large peak inflow
         awarded to Barge by WTRBA, including   also confirmed the need to use HEC-RAS   of around 1,400 cubic feet per section
         the Tiptonville pump station, a permanent   2-Dimensional (2D) modeling to develop   during the 100-year rainfall event due to
         stormwater pumping solution to mitigate   inflows required for input into the pump   limitations in the modeling approach. The
         flood risk in the community.        station design.                      projected inundation elevations seemed to
           “While there were multiple qualified   “Using 2D models instead of traditional   exceed those of the existing conditions. As
         consultants, Barge was elevated because of   TR-55 models is relatively new and is   a result, a new 2D model was developed.
         their specific experience with stormwater   generally chosen for very flat terrain and   New LiDAR data was used to build a 2D
         and stormwater pump station projects,”   areas where large amounts of overland flow   computational mesh, and excess rainfall
         Blackwood said. “They also had the staff   are expected,” Cropp said. “To produce   amounts were applied to that mesh.  As
         and experience to deliver the projects.   a more realistic hydrologic response, we   excess rainfall was applied to individual
                                                                                  cells within the mesh, water accumulated
                                                                                  was conveyed downstream from one cell to
                                                                                  the next until it reached the outfall. 
                                                                                   Each cell had its own set of hydraulic
                                                                                  properties and allowed the software
                                                                                  to compute a combined discharge
                                                                                  hydrograph based on the response of each
                                                                                  individual cell.   
                                                                                   The results showed that the existing flat
                                                                                  topography had a large attenuation effect
                                                                                  on the discharge hydrograph. The result?
                                                                                  To optimize the design for the greatest
                                                                                  benefit to the community and the least
                                                                                  financial impact, the team concluded that
                                                                                  a total pumping capacity of 30,000 gallons
                                                                                  per minute would be needed for the pump
                                                                                  station. 
                                                                                  Pump Station Design Takes Shape
                                                                                   WTRBA selected a 10-year rain event
                                                                                  for the basis of the final design, meaning
                                                                                  two 21,000 gpm pumps would be presented
                                                                                  in Barge’s plan. This design threshold
                Designers worked with the U.S. Army Corps of Engineers to protect the levee from excavation,   translates to an overall risk below the one
                choosing to build up and over the structure to maintain its integrity, while also making it drivable.  Continued on page 8

                                                                                        View online at tnpublicworks.com   7
   2   3   4   5   6   7   8   9   10   11   12