Page 27 - Jan/Feb 2023 Vol 40 No 6
P. 27

and processes. For example, a street
         centerline layer was used as the base
         layer for analysis, and other datasets
         were analyzed for each of the four critical
         factors. The safety factor utilized traffic
         incidents involving pedestrians and
         cyclists, respectively.
         Safety, Transit, Connectivity, and Equity
           The ratio of number of incidents
         relative to the street length determined
         the safety score. The connectivity score
         was based on the percentage of existing                                             Stakeholder Engagement Meeting
         sidewalk on a given street segment. The   disabled population, senior population,
         transit score for a street segment was   female population, less than high   CRITERIA   ISSUE TO MITIGATE
         based on proximity to transit stops.   school education, limited English
         Scoring varied based on number of   speaking households, total minority   Safety     Would a project
         boardings and alighting for a given   population, population in poverty,             address a location with
         transit stop.                       renters, unemployed workers, and youth           a documented safety
           The equity score came from analysis   population.                                  concern?
         using data from the Greater Nashville   Once the analysis was complete, a
         Regional Council (GNRC) that        total score reflecting all four factors   Health &    Would a project
         determined areas with Degrees of    was added to the attributes of each   Equity     benefit underserved
         Vulnerability (DOV). Scores were based   street segment. After analyzing and         communities?
         on streets intersecting census tracts   processing the GIS data, the next step   Transit   Would a project improve
         categorized as either “Vulnerable” or   was site selection while considering   Access   pedestrian access to the
         “Highly Vulnerable”.                constructability. Any existing projects
           These categories were based on    that NDOT was already committed to               transit network?
         thirteen factors including: active   were scored and compared spatially to   Connectivity  Would a project support
         transportation commuters, carless   the street network.                              the existing network?
         households, housing cost burdened,                     continued on page 28














































                                                                                        View online at tnpublicworks.com   27
   22   23   24   25   26   27   28   29   30   31   32