Master Plan in Action from page 7            evaluated flow diversions and parallel          because they were outside of the Federal
                                             drainage systems to alleviate flooding.         Emergency Management Agency (FEMA)
  Once the PCSWMM model was                                                                  Special Flood Hazard Area.
implemented, the results were calibrated       In addition, Germantown saw a
to ensure it accurately represented the      window of opportunity for collaborating           With the Stormwater Master Plan
system and could be used to evaluate         with developers through their required          already underway, City officials were able
flood mitigation alternatives. The model’s   regulations and standards. New                  to reassure the public that they foresaw
implementation also created risk maps by     developments still were being constructed;      the potential flooding issues, were already
using building footprints and LiDAR data     a process likely to continue as the City        working to resolve the concerns, and
to identify structures at a greater risk of  grows. Developers must answer to certain        would approach this effort with new vigor.
flooding.                                    infrastructure obligations, so the City         Germantown’s relationship with Barge
                                             leveraged developers’ capabilities to           meant the City was not only prepared to
  Structures were color-coded on the         assist in fixing the stormwater drainage        communicate a plan to the community,
risk map to assist in quickly identifying    network.                                        but they also had Barge’s help with
problem areas. The Barge Information                                                         engaging their constituents.
Management team created a custom tool          For instance, if a development is
with GIS capabilities, which uses the        progressing in an identified problem              Environmental events can wreak
model’s results to generate the LOS for      basin, the City could require over-             havoc on a community and are beyond
each structure. In terms of this process,    detention. Collaboration and                    the control of even the most efficient
the LOS rating indicates the return period   communication between the developer             and effective governments. These newly-
each asset could accommodate.                and the City allows for better management       implemented capabilities and technologies
                                             of the development’s impact on the              empower Germantown to respond to
  Applying these technologies                overall drainage system, not just the pipe      immediate needs or events confidently
modernized the City’s data collection and    downstream.                                     and quickly.
provided access to real-time, accurate
information. This allowed Germantown to        Precise awareness of their stormwater         The Results of Effective Collaboration
confidently identify drainage basins with a  system enabled Germantown the ability
low LOS and continue to the next phase of    to see the larger picture, which alerted          Now, twenty years after the City’s
the master plan.                             them to opportunities to combine                growth spurt, prompting the actions
                                             projects. This not only saved funding and       taken to develop the master plan and
Efforts Taking Shape                         staffing resources, it also created greater     related efforts, Germantown has earned
                                             accountability between the City and             the Malcolm Baldrige National Quality
  Determining where to start was only        developers.                                     Award. Given to only four municipalities
part of the equation. Barge and the City                                                     since its inception in 1987, this is a
of Germantown were now faced with            Remediation Efforts in Action                   prestigious recognition of an entity’s
the task of finding creative solutions to                                                    quality in organization and efficiency.
a multi-faceted issue affecting the entire     While no municipality wants to face a
city. Though the assets with the lowest      crisis, preparation is essential. Through         The criteria to be considered are
LOS scores were identified, the solution     the geodatabase and the modeling                excellence in: leadership; strategy;
could not be contained to those basins.      system, City staff can evaluate emergent        customer relations; measurement,
                                             needs quickly, like in the storm event          analysis, and knowledge management;
  A problem of this magnitude and in         experienced on June 7, 2019, when an area       workforce; operations; and results. The
such highly-developed areas required         of Germantown received almost 10 inches         Stormwater Master Plan represents one
innovative solutions. Simply making pipes    of rain in less than four hours.                in a multitude of intentional decisions
or conduits larger in one area only moves                                                    that helped the City achieve this
the problem downstream. With this in           That June rain event was estimated            commendation, and emphasizes their
mind, the City evaluated new detention       to have a greater than 10,000-year-             dedication to creating a smarter, safer
basins within existing developments,         recurrence interval for precipitation. It left  community through innovation and
expanded existing detention basins, and      more than 100 homes flooded, 90 percent         collaboration.