Page 14 - May-June2019 Vol37 No1
P. 14

Vital Connection from page 13                 closely with MWS, Metro Public Works         a Triple bottom line (TBL) analysis
                                              and TDOT to complete the project on          was prepared to quantify the overall
and Lebanon Pike required jacking and         an expedited schedule. Working around        economic, social and environmental
boring to keep a major railroad crossing      the clock, the project was completed in      impacts.
open.                                         less than 24 months, saving millions of
Tracing the Loop                              dollars for MWS and mitigating impact          In this context, by creating supply
                                              to the public.                               redundancy for the MWS service area
  A 60" x 60" DIP Tee with two 60-inch                                                     east of the Stones River, this project
gate valves on either side was used to          The new route and distribution points      improved CCL’s transmission water main
connect the 60-inch replacement section       add enough capacity to the system that in    resilience against the acute shock of a
of transmission main on McGavock Pike         the event one water treatment plant goes     water main break.
to the new 60-inch transmission main          offline in an emergency, sufficient water
routed toward the eastern portion of the      still could be effectively supplied to the     As evidenced in the TBL analysis, there
distribution system.                          east side of Nashville.                      are current and future positive impacts
                                                                                           from infrastructure spending. In the case
  An MWS cost savings of $75,000                In summary, the new water                  of the CCL project, post-construction,
resulted from creation of an 84-inch          transmission main pushes water via a         the redundancy accomplished by the
diameter tunnel routing the new section       continuous loop that can accommodate         project is estimated to avoid $5.5 million
of 60-inch ductile iron pipe beneath the      flow in either line, as needed, to           of additional expense and lost revenue
Nashville Eastern Railroad Crossing           accommodate system water demand.             in the communities east of the Stones
near Donelson Pike. (The design team’s        The new water transmission main              River, in the event of future water supply
decision to reduce the tunnel’s diameter      also provides increased reliability for      disruptions.
from 96 inches to 84 inches and shorten       delivering clean water to the eastern
its length played a significant factor        portion of Davidson County.                    During construction, over 100
here.)                                                                                     estimated jobs were supported, many
                                                This system is better prepared to          of them stable infrastructure positions;
  Garney Construction managed a               handle a break, due to the increased         an estimated $3.1 million in taxes
500-foot-long construction zone in            flexibility and the variety of directions    were collected across federal, state
an area with a high volume of traffic,        water can be pushed from either K.R.         and local jurisdictions; an estimated
moving the zone down the street               Harrington or Omohundro—or both              $8.7 million in future construction
concurrently with construction efforts        plants. As a result, the water distribution  costs were avoided by strategically
to avoid blocking the entire length of        system is a more reliable infrastructure     upsizing a portion of the line to 60-
the street, minimizing impact to traffic.     for MWS customers.                           inch pipe; and a verified $6.1 million of
This was particularly important since         A Socioeconomic and Environmental            construction was awarded to small or
the 60-inch transmission main was laid        Win-Win                                      disadvantaged businesses supporting
in the middle of some of Nashville’s                                                       the project. Moreover, an estimated 1.4
central traffic routes, which are also state    While aging infrastructure systems         years of additional traffic congestion
highways managed by the Tennessee             pose major issues, well-planned strategic    was avoided; $1.3 million in wasted
Department of Transportation (TDOT)           infrastructure projects often provide        commuter work time and travel fuel
and Metro Public Works, including             exponential benefits both economically       was averted; and $46 million of public
Donelson Pike—the main route to and           and to the community. The CCL                health and other external environmental
from Nashville International Airport          Transmission Water Main project              costs were avoided due to the expedited
from the north.                               identifies multiple social, economic and     construction schedule that was built into
                                              environmental benefits to communities        the project approach.
  Part of the 36-inch water main              similar to Nashville, in terms of how        The Cumberland City Lowdown
alignment involved crossing the Stones        infrastructure improvements can help
River near Lebanon Pike. Starting on the      cities survive, adapt and grow.                Without this project, MWS would still
west side of the Stones River, a temporary                                                 have only one water transmission line
Portadam was created to pump out river          Economic benefits included jobs            across the Stones River connecting the
water allowing workers to dig below the       sustained during the project as well as      entire eastern portion of its vital water
riverbed to lay this section of 36-inch       projected growth in economic activity.       distribution system, creating a less than
water main. Coordination with the             Social and environmental impacts were        optimal situation for the customers
United States Army Corps of Engineers         projected via literature reviews, data       they serve. With this project, MWS has
was required during this portion of the       analysis, and interviews with project        improved reliability, redundancy, and
construction to regulate the flow from        staff. Benefits included increased           resiliency systemwide, which benefits
Percy Priest Lake into the Stones River.      resilience and reduced traffic congestion.   the Nashville community by providing
                                                                                           a safe, clean and reliable water source.
  Once complete, the same process               Environmental impacts were expressed       New paving, spruced-up sidewalks, and
was employed on the east side of the          as the estimated reductions in external      plantings along the former project route
river, with the water transmission main       costs to the community when traffic          are yet another positive byproduct of
ultimately tying into the existing 24-inch    congestion is reduced. When compared         one of the largest diameter high-pressure
line at Central Pike, thereby completing      to MWS’ already high level of service        pipeline projects in Metro Nashville
the water system loop.                        and regulatory compliance, supply            history.
                                              redundancy was the benefit yielding the
  Gresham Smith engineers worked              greatest impact. As part of this project,

14	 TPW May/June 2019
   9   10   11   12   13   14   15   16   17   18   19