Page 14 - May-June2019 Vol37 No1
P. 14
Vital Connection from page 13 closely with MWS, Metro Public Works a Triple bottom line (TBL) analysis
and TDOT to complete the project on was prepared to quantify the overall
and Lebanon Pike required jacking and an expedited schedule. Working around economic, social and environmental
boring to keep a major railroad crossing the clock, the project was completed in impacts.
open. less than 24 months, saving millions of
Tracing the Loop dollars for MWS and mitigating impact In this context, by creating supply
to the public. redundancy for the MWS service area
A 60" x 60" DIP Tee with two 60-inch east of the Stones River, this project
gate valves on either side was used to The new route and distribution points improved CCL’s transmission water main
connect the 60-inch replacement section add enough capacity to the system that in resilience against the acute shock of a
of transmission main on McGavock Pike the event one water treatment plant goes water main break.
to the new 60-inch transmission main offline in an emergency, sufficient water
routed toward the eastern portion of the still could be effectively supplied to the As evidenced in the TBL analysis, there
distribution system. east side of Nashville. are current and future positive impacts
from infrastructure spending. In the case
An MWS cost savings of $75,000 In summary, the new water of the CCL project, post-construction,
resulted from creation of an 84-inch transmission main pushes water via a the redundancy accomplished by the
diameter tunnel routing the new section continuous loop that can accommodate project is estimated to avoid $5.5 million
of 60-inch ductile iron pipe beneath the flow in either line, as needed, to of additional expense and lost revenue
Nashville Eastern Railroad Crossing accommodate system water demand. in the communities east of the Stones
near Donelson Pike. (The design team’s The new water transmission main River, in the event of future water supply
decision to reduce the tunnel’s diameter also provides increased reliability for disruptions.
from 96 inches to 84 inches and shorten delivering clean water to the eastern
its length played a significant factor portion of Davidson County. During construction, over 100
here.) estimated jobs were supported, many
This system is better prepared to of them stable infrastructure positions;
Garney Construction managed a handle a break, due to the increased an estimated $3.1 million in taxes
500-foot-long construction zone in flexibility and the variety of directions were collected across federal, state
an area with a high volume of traffic, water can be pushed from either K.R. and local jurisdictions; an estimated
moving the zone down the street Harrington or Omohundro—or both $8.7 million in future construction
concurrently with construction efforts plants. As a result, the water distribution costs were avoided by strategically
to avoid blocking the entire length of system is a more reliable infrastructure upsizing a portion of the line to 60-
the street, minimizing impact to traffic. for MWS customers. inch pipe; and a verified $6.1 million of
This was particularly important since A Socioeconomic and Environmental construction was awarded to small or
the 60-inch transmission main was laid Win-Win disadvantaged businesses supporting
in the middle of some of Nashville’s the project. Moreover, an estimated 1.4
central traffic routes, which are also state While aging infrastructure systems years of additional traffic congestion
highways managed by the Tennessee pose major issues, well-planned strategic was avoided; $1.3 million in wasted
Department of Transportation (TDOT) infrastructure projects often provide commuter work time and travel fuel
and Metro Public Works, including exponential benefits both economically was averted; and $46 million of public
Donelson Pike—the main route to and and to the community. The CCL health and other external environmental
from Nashville International Airport Transmission Water Main project costs were avoided due to the expedited
from the north. identifies multiple social, economic and construction schedule that was built into
environmental benefits to communities the project approach.
Part of the 36-inch water main similar to Nashville, in terms of how The Cumberland City Lowdown
alignment involved crossing the Stones infrastructure improvements can help
River near Lebanon Pike. Starting on the cities survive, adapt and grow. Without this project, MWS would still
west side of the Stones River, a temporary have only one water transmission line
Portadam was created to pump out river Economic benefits included jobs across the Stones River connecting the
water allowing workers to dig below the sustained during the project as well as entire eastern portion of its vital water
riverbed to lay this section of 36-inch projected growth in economic activity. distribution system, creating a less than
water main. Coordination with the Social and environmental impacts were optimal situation for the customers
United States Army Corps of Engineers projected via literature reviews, data they serve. With this project, MWS has
was required during this portion of the analysis, and interviews with project improved reliability, redundancy, and
construction to regulate the flow from staff. Benefits included increased resiliency systemwide, which benefits
Percy Priest Lake into the Stones River. resilience and reduced traffic congestion. the Nashville community by providing
a safe, clean and reliable water source.
Once complete, the same process Environmental impacts were expressed New paving, spruced-up sidewalks, and
was employed on the east side of the as the estimated reductions in external plantings along the former project route
river, with the water transmission main costs to the community when traffic are yet another positive byproduct of
ultimately tying into the existing 24-inch congestion is reduced. When compared one of the largest diameter high-pressure
line at Central Pike, thereby completing to MWS’ already high level of service pipeline projects in Metro Nashville
the water system loop. and regulatory compliance, supply history.
redundancy was the benefit yielding the
Gresham Smith engineers worked greatest impact. As part of this project,
14 TPW May/June 2019

