Page 18 - Jan-Feb 2020
P. 18

TCAPWA 2019 MARK MILLER PROJECT OF THE YEAR                                                    By Colline Miller MPA

Chattanooga’s Big Dig:
Protecting People and Their Water

Background                                      a plan to re-route the existing storm          cal schools, and events for the timing of
  The historic district of St. Elmo in Chat-    infrastructure around the landfill. The        the closure of Broad Street (a primary
                                                plan consisted of 1,360 feet of 10'x10' box    roadway).
tanooga, Tennessee is located in the valley     culvert at depths reaching over 30 feet        Energy Dissipation
of Lookout Mountain near the Tennessee          deep, 200 feet of 8'x8' box culvert, 630 feet
River. Storm drainage for the St. Elmo area     of 60" reinforced concrete pipe (RCP), 230       A major design challenge was the
outfalls into Chattanooga Creek at the curl     feet of 54" RCP and 400 feet of 36" RCP,       accommodation of a significant peak
in the Tennessee River referred to as Moc-      including 3 tunnels (2-78" tunnels under       stormwater flow (1,900 CFS) and
casin Bend.                                     Norfolk Southern Railroad and 1-96"            dissipating the energy of such a flow
                                                tunnel under the parking lot of a dialysis     reaching Chattanooga Creek. A 100-year
  The existing area storm infrastructure        clinic). The project coordinated with the      peak storm event would decimate the
consisted of different pipe sizes and materi-   St. Elmo Riverwalk project to include          existing banks of the creek at the outfall
als that had been added on to and extended      installation of sidewalks, bike lanes and      without dissipation of the flow velocity.
over many years. Area storm water (ap-          streetscape features.                          Civic’s engineers had to balance slowing
proximately 1,100 acres) fed into a 10'x7'      Uniqueness/Innovation: New or Existing         the flow to an acceptable velocity while
corrugated metal pipe that extended over        Technology                                     maintaining hydraulic grades upstream.
30 feet below the now capped Wheland
Foundry Landfill.                                 The Chattanooga “Big Dig” provides the         The solution included an array of
                                                storm drainage backbone to accommodate         uniquely-designed reinforced concrete
  The City of Chattanooga desired to            a 100-year storm event for a 1,100-acre        energy dissipation blocks at the outfall
perform a hydraulic study and structural        drainage area encompassing the historic St.    followed by a 120' long gabion block
evaluation of the existing storm convey-        Elmo District, large parts of Alton Park and   lined channel with gabion baffles. The
ance to evaluate existing conditions and        South Chattanooga with one outfall into        combined utilization of different materials
determine requirements to redirect storm        Chattanooga Creek, which is a tributary to     and dissipation methods resulted in an
conveyance around the landfill. The City        the Tennessee River. Harnessing the power      outfall that can handle both maximum
contracted Civic Engineering and Informa-       of the potential water volume from this        and minimum flows.
tion Technologies, Inc. (Civic) to perform      large of an area created extreme challenges.   Maintenance Considerations
the study.
                                                  This project was not only massive in           In order to make sure the City can
  The findings indicated that existing          size and volume, it was equally massive in     maintain the system and keep it operating
infrastructure was undersized for existing      its required planning and coordination.        properly, the reinforced concrete energy
stormwater flows as suspected, and that the     The impact to vehicular and pedestrian         dissipaters at the outfall were spaced to al-
pipe under the landfill was extremely dete-     traffic had to be managed and required         low a skid steer loader to enter at the out-
riorated and needed to be addressed in an       coordination with property owners, lo-         fall, to assist with the removal of sediment
expeditious manner. A collapse of this pipe
would not only cause flooding throughout
the St. Elmo area, but it could also leach the
landfilled foundry sand into the Chatta-
nooga Creek and Tennessee Rivers.

  To prevent a catastrophic failure of their
stormwater infrastructure and poten-
tial water contamination from a former
landfill, the City of Chattanooga took
action to redesign the storm conveyance
in the historic St. Elmo area of the city. The
discovery of contaminated soils compli-
cated the project and brought in additional
stakeholders.

  The new storm drainage is designed to
accommodate a 100-year storm event. The
new infrastructure has been designed with
expansion in mind to pave the way for
future development of the area.
The Plan

  At the City’s request, Civic developed

18	 TPW January/February 2020
   13   14   15   16   17   18   19   20   21   22   23