Page 19 - Jan-Feb 2020
P. 19
buildup or large debris. A junction box at manner that contains and/or disposes the storm conveyance that was believed to
the far upstream end of the project and an contaminants to keep the public safe from run underneath the Wheland Foundry
intermediate structure was constructed so exposure, and what the project accom- Landfill. What was found was a highly
that the tops can be lifted off by crane to plishes for stormwater capacity and future deteriorated hodgepodge of partially
allow a skid steer loader to be lowered in development. collapsed and eroded corrugated metal
for future maintenance. Social, Economic, and Sustainable pipes, box culverts, and parallel pipes that
Pre-construction Soil and Groundwater Development Considerations did, in fact, run under the landfill. The
Characterization City was on the clock. They knew that if
The stormwater infrastructure (that was the deteriorated pipe under the landfill
For construction planning purposes, in place previous to the Big Dig project) were to fully fail, it could have major
S&ME was initially contracted by the was undersized and already was partially flooding and environmental implications.
City to evaluate soil and groundwater collapsed. The project limits were pri- Structural Design
conditions along the horizontal and marily in an industrial area where many
vertical extent of the proposed stormwater properties have been vacant or dormant The proposed storm infrastructure
alignment. A total of 165 soil samples for decades. While this project was driven was very large and very deep (ranging
were collected from 54 soil borings primarily due to the condition of the ex- from 22' to 30' below grade). Civic’s
and four groundwater samples from isting storm conveyance and environmen- engineers worked with multiple precast
monitoring wells positioned along the tal impact concerns, the project ties in to a manufacturers of the design options
three proposed conveyances. larger effort to revitalize the St. Elmo and for the storm conveyances. However,
Southern Chattanooga areas for invest- the outfall structure and junction boxes
The assessment activities identified the ment and development. had to be specially designed. The outfall
presence of polynuclear aromatic hydro- structure required reinforced concrete
carbons (PAHs), eight Resource Conser- The City has been in the process of energy dissipaters that can stand up to high
vation and Recovery Act (RCRA) metals extending the Chattanooga Riverwalk velocity flows that may contain large debris.
and extractable petroleum hydrocarbons from the downtown riverfront to the Additionally, the upstream junction box
(EPH) in soil and groundwater. For soil historic St. Elmo area. A portion of the was three stories high and designed to tie
samples containing metals concentrations planned Riverwalk was incorporated into in to the existing upstream infrastructure
approaching or exceeding 20 times the the project, providing a key connection while allowing for bypass flow through the
US EPA Toxicity Characteristic Regula- to the upcoming Riverwalk project for structure during construction.
tory Level, the samples also were analyzed pedestrian and bicycle activity. Continuous On-site Soil Management
for the target constituents using the EPA
Toxicity Characteristic Leaching Proce- Extensive forethought went into the Previous soil investigations conducted
dure (TCLP). design project. The storm infrastructure by S&ME identified the presence of im-
that was installed with this project pacted fill materials with contaminants that
The assessments resulted in valuable was sized and stubbed out in multiple rendered soils both non-hazardous special
data necessary to support negotiation of a locations along the alignment for waste as well as materials that exceed char-
Brownfield Voluntary Agreement for the anticipated future expansion and acteristically hazardous threshold. S&ME
easement, provide recommendations and development. The Big Dig Project will provided day to day on-site monitoring
protocols for management of foundry- serve as the backbone to pave the way for services utilizing photo-ionization and x-
related waste and hazardous and special the future development in the area. ray fluorescence instrumentation that kept
waste as well as petroleum and metals Complexity the contractors, Civic, City, and TDEC ap-
contaminated groundwater along the prised of site soil conditions continuously
portion of the alignment outside of the Asset Inventory, Condition Analysis, for the duration of the project. The real
landfill footprint. Hydrology, Hydraulics, Geotechnical time evaluation of site soil conditions as-
Bringing Public Awareness of the Role of Engineering, Structural Design, Soil and sisted the contractor to direct the excavated
Public Works and Engineering in Society Groundwater Characterization, Utility materials for reuse on-site as structural
Design/Coordination, Environmental fill, clean cover soils and off-site landfill
The public often is not aware of storm Permitting, Wildlife Protection, Traffic disposal as special waste.
infrastructure until there is a problem. Control, Hazardous and Non-hazardous Utility Design/Coordination
The City of Chattanooga identified Soil and Groundwater Management, Logis-
structural and capacity issues for the tics, Railroad Permitting, R.O.W./Easement The project required the relocations of
existing storm infrastructure conveyance Acquisition, Construction Inspection/Ad- gravity sanitary sewer, sanitary force main,
under the Wheland Foundry Landfill, ministration, Scheduling, Public Relations: existing storm drainage, water lines, gas
proactively putting a plan in action to This list sounds like a pretty well-rounded lines, overhead utilities and even hydrogen
relocate and upsize the existing storm engineering curriculum, but these were lines.
infrastructure to ultimately avoid a some of the key disciplines required to de- Traffic Control
catastrophic failure that would have both sign and execute the Chattanooga Big Dig
environmental and flooding impacts. project. This project was one archeological Traffic control was integral in the success
find away from having everything! of this project. The project required the
Through public meetings, The City of Asset Inventory and Condition Analysis 60-day closure of Broad Street (Cummings
Chattanooga was able to spread awareness Highway), which is one of only two main
about the project, discussing topics such One of the first objectives of this
as the finding of contaminated soils, how project was to perform an inventory Continued on page 21
the project would address the soils in a and condition assessment of the existing
View online at tnpublicworks.com 19