Page 7 - March-April2021 Vol 38 No 7
P. 7

I-440 Bridge over I-65, Franklin Road and CSX Railroad. ©AERIAL INNOVATIONS     asphalt, the addition of a third travel
                                                                                lane in each direction, and ramp safety
Gantry used to roll girders into position. ©WSP USA                             improvements at the 21st Avenue and
                                                                                Murphy Avenue exits.

                                                                                  Work also entailed the widening of
                                                                                three bridges, removal of an elevated
                                                                                median, upgrades to the intelligent
                                                                                transportation system (ITS) and roadway
                                                                                lighting, noise walls, rock fall mitigation
                                                                                and landscaping improvements. The
                                                                                I-440 over I-65 and CSX Railroad was
                                                                                one of the most challenging aspects, and
                                                                                was the largest potential risk factor for
                                                                                delaying the schedule. The work required
                                                                                the widening of a pair of 1000-ft-long
                                                                                bridges on the fourth level of the system
                                                                                interchange.
                                                                                Design-Build Team & Process

                                                                                  TDOT awarded the project to the
                                                                                Kiewit Infrastructure South with WSP
                                                                                USA Inc. serving as the Team’s designer
                                                                                on August 1, 2018. The DB schedule
                                                                                for completion was set at 708 days. The
                                                                                project included a disincentive, if not
                                                                                completed on-time, of $100,000 per
                                                                                day for the first 30 days and $400,000
                                                                                each day after. This was a substantial
                                                                                motivator for all parties involved.

                                                                                  Throughout the Fall of 2018, design
                                                                                progressed, permits were secured,
                                                                                utility coordination and constructability
                                                                                reviews and approvals from TDOT,
                                                                                FHWA, and vendor shop drawings
                                                                                were well underway. The DB Team,
                                                                                with TDOT’s approval, released a series
                                                                                of Early-Works Packages that focused
                                                                                on critical elements that needed to be
                                                                                constructed prior to other activities.

                                                                                  This work included new noise
                                                                                walls, relocation of existing fiber, and
                                                                                two ramp terminal improvement
                                                                                projects. These Early-Works packages
                                                                                were approved for construction by
                                                                                November 2018, which allowed limited
                                                                                construction to start in December 2018.
                                                                                Heavy construction commenced in
                                                                                earnest in early 2019.
                                                                                Pavement Rubblization

                                                                                  One of the significant achievements in
                                                                                this project was the implementation of
                                                                                a highly successful rubblization process.
                                                                                Rubblization for the I-440 project
                                                                                involved the crushing of the top layer of
                                                                                the concrete pavement, which was then
                                                                                recycled for use as graded base material
                                                                                for the final asphalt pavement.

                                                                                                                        Continued on page 8

                                                                             	  View online at tnpublicworks.com	  7
   2   3   4   5   6   7   8   9   10   11   12