Page 7 - May-June2019 Vol37 No1
P. 7
SITE LAYOUT document the ultimately saving the client approximately
is understanding the site’s utilities prior project team could $1 million.
to beginning the design. The same rang find, there wasn’t
true with HHS, mostly due to the age a clear answer as While the cost savings was welcomed
of the campus, the number of previous to the location of by MNPS, this stormwater management
renovations and the lack of historic civil the water’s final solution meant that every available open
design documents. drainage area. It space on the tight, landlocked site would
seemed to drift off now be occupied by bioretention ponds.
Our team began with an in-depth into no man’s land In fact, space was at such a premium
due diligence research effort to better where the most on the HHS campus that bioretention
understand the site’s existing flows to logical downstream ponds often had to be placed closer to
public storm infrastructure and how catch basin was structures than MWS’ recommended
it related to the site’s existing drainage full of concrete offset distances.
basins. During our initial due diligence, from a previous
we discovered three major utility design construction Due to the design challenge, our team
challenges affecting the site. project. coordinated often with the project’s
structural engineer to ensure the angle of
First, a public sanitary sewer line However, after repose for the buildings’ footings didn’t
snaked its way through the center of multiple trips to fall within the bioretention ponds’ loose,
the site under the current football field. the site, TDOT was able to chisel away uncompacted area. The final design of
We relocated a portion of the line and concrete and use a camera to explore HHS encompassed seven bioretention
it caused minimal interruption to our the stormwater network. To the surprise ponds with a total treatment volume of
design. of the entire project team, there was 40,000 cubic feet, 10,000 linear feet of
a trunk line sewer running down the pipe, more than 150 storm structures and
Our second surprise came when center of Hillsboro Pike that was blindly 3,500 man hours of planning, design and
Nashville Metro Water Services (MWS) connected to every inlet. Ultimately, plan production.
informed us that a major stormwater our team redesigned the trunk sewer Going Back to School
trunk line sewer was running through to increase the capacity of the storm
the campus. It was believed to be a piped network. HHS students weren’t the only
stream that was constantly flowing in a If stormwater surprises weren’t ones learning on that campus—our
50-square-foot riparian area where the enough, our team also discovered project team learned a thing or two
stream daylighted, which meant we had unusual site conditions while excavating as well. When updating existing sites
to get additional permitting from the for a small parking lot. The fill never to comply with current stormwater
U.S. Army Corp of Engineers and the had been compacted, and it contained regulations, it can be challenging, costly
Tennessee Department of Environmental blocks and stumps, which were parts and full of surprises. Engineers and
Conservation (TDEC) for a stream of basements from houses that were developers frequently find themselves
relocation. While the project’s timeline demolished there in the early 1950s and updating infrastructure that has become
wasn’t affected by the added permit 1960s. insufficient due to growth and age.
process, we did have to account for a The Best Bet: Bioretention Ponds
shallow riddle pool in our final design. In 2016, MWS implemented Land is often at such a premium that
mandatory development regulations that buildings are built-out to the fullest
Finally, our largest surprise came when require all site designs to utilize green extent possible, allowing minimal
our team discovered storm drainage in infrastructure to meet stormwater runoff room for green space and stormwater
the right-of-way. Even after multiple water quality (unless a hardship, such as infrastructure. Additionally, due to
discussions with MWS and the Tennessee karst, can be demonstrated). Although updated standards and regulations,
Department of Transportation (TDOT), low impact development practices were a sometimes only a fraction of an existing
as well as pulling every historical requirement, our design team saw HHS site will be suitable for redevelopment
as the perfect project to demonstrate without substantial additional
different options for stormwater permitting.
infiltration practices.
Initially, our design called for 20,000 While small urban spaces often
square feet of pervious paving, 15,000 present a slew of site challenges, they
square feet of bioretention ponds, 9,500 are often the perfect place to implement
square feet of green roof, and 3,000 square low impact development practices.
feet of bioswale. After a pricing estimate As Nashville continues to expand and
from an independent contractor, we redevelopment projects become more
needed to make cuts to stay within the prominent, complex site problems will
original $73 million dollar budget. We likely become the new normal.
decided to eliminate the green roof, as
well as most of the pavers and bioswale, in Close, careful coordination between
favor of an all bioretention pond system, the project team and public works
can address the unique needs of our
cities, improving public infrastructure
while limiting the impact on our built
environment and enhancing quality of
life for residents and visitors alike.
View online at tnpublicworks.com 7