Page 7 - May-June2019 Vol37 No1
P. 7

SITE LAYOUT                                                         document the         ultimately saving the client approximately
is understanding the site’s utilities prior                           project team could   $1 million.
to beginning the design. The same rang                                find, there wasn’t
true with HHS, mostly due to the age                                  a clear answer as      While the cost savings was welcomed
of the campus, the number of previous                                 to the location of   by MNPS, this stormwater management
renovations and the lack of historic civil                            the water’s final    solution meant that every available open
design documents.                                                     drainage area. It    space on the tight, landlocked site would
                                                                      seemed to drift off  now be occupied by bioretention ponds.
  Our team began with an in-depth                                     into no man’s land   In fact, space was at such a premium
due diligence research effort to better                               where the most       on the HHS campus that bioretention
understand the site’s existing flows to                               logical downstream   ponds often had to be placed closer to
public storm infrastructure and how                                   catch basin was      structures than MWS’ recommended
it related to the site’s existing drainage                            full of concrete     offset distances.
basins. During our initial due diligence,                             from a previous
we discovered three major utility design                              construction            Due to the design challenge, our team
challenges affecting the site.                                        project.             coordinated often with the project’s
                                                                                           structural engineer to ensure the angle of
  First, a public sanitary sewer line                                    However, after    repose for the buildings’ footings didn’t
snaked its way through the center of                                  multiple trips to    fall within the bioretention ponds’ loose,
the site under the current football field.   the site, TDOT was able to chisel away        uncompacted area. The final design of
We relocated a portion of the line and       concrete and use a camera to explore          HHS encompassed seven bioretention
it caused minimal interruption to our        the stormwater network. To the surprise       ponds with a total treatment volume of
design.                                      of the entire project team, there was         40,000 cubic feet, 10,000 linear feet of
                                             a trunk line sewer running down the           pipe, more than 150 storm structures and
  Our second surprise came when              center of Hillsboro Pike that was blindly     3,500 man hours of planning, design and
Nashville Metro Water Services (MWS)         connected to every inlet. Ultimately,         plan production.
informed us that a major stormwater          our team redesigned the trunk sewer           Going Back to School
trunk line sewer was running through         to increase the capacity of the storm
the campus. It was believed to be a piped    network.                                        HHS students weren’t the only
stream that was constantly flowing in a        If stormwater surprises weren’t             ones learning on that campus—our
50-square-foot riparian area where the       enough, our team also discovered              project team learned a thing or two
stream daylighted, which meant we had        unusual site conditions while excavating      as well. When updating existing sites
to get additional permitting from the        for a small parking lot. The fill never       to comply with current stormwater
U.S. Army Corp of Engineers and the          had been compacted, and it contained          regulations, it can be challenging, costly
Tennessee Department of Environmental        blocks and stumps, which were parts           and full of surprises. Engineers and
Conservation (TDEC) for a stream             of basements from houses that were            developers frequently find themselves
relocation. While the project’s timeline     demolished there in the early 1950s and       updating infrastructure that has become
wasn’t affected by the added permit          1960s.                                        insufficient due to growth and age.
process, we did have to account for a        The Best Bet: Bioretention Ponds
shallow riddle pool in our final design.       In 2016, MWS implemented                      Land is often at such a premium that
                                             mandatory development regulations that        buildings are built-out to the fullest
  Finally, our largest surprise came when    require all site designs to utilize green     extent possible, allowing minimal
our team discovered storm drainage in        infrastructure to meet stormwater runoff      room for green space and stormwater
the right-of-way. Even after multiple        water quality (unless a hardship, such as     infrastructure. Additionally, due to
discussions with MWS and the Tennessee       karst, can be demonstrated). Although         updated standards and regulations,
Department of Transportation (TDOT),         low impact development practices were a       sometimes only a fraction of an existing
as well as pulling every historical          requirement, our design team saw HHS          site will be suitable for redevelopment
                                             as the perfect project to demonstrate         without substantial additional
                                             different options for stormwater              permitting.
                                             infiltration practices.
                                               Initially, our design called for 20,000       While small urban spaces often
                                             square feet of pervious paving, 15,000        present a slew of site challenges, they
                                             square feet of bioretention ponds, 9,500      are often the perfect place to implement
                                             square feet of green roof, and 3,000 square   low impact development practices.
                                             feet of bioswale. After a pricing estimate    As Nashville continues to expand and
                                             from an independent contractor, we            redevelopment projects become more
                                             needed to make cuts to stay within the        prominent, complex site problems will
                                             original $73 million dollar budget. We        likely become the new normal.
                                             decided to eliminate the green roof, as
                                             well as most of the pavers and bioswale, in     Close, careful coordination between
                                             favor of an all bioretention pond system,     the project team and public works
                                                                                           can address the unique needs of our
                                                                                     	     cities, improving public infrastructure
                                                                                           while limiting the impact on our built
                                                                                           environment and enhancing quality of
                                                                                           life for residents and visitors alike.

                                                                                           View online at tnpublicworks.com	  7
   2   3   4   5   6   7   8   9   10   11   12