Page 7 - May-June 2021 Vol 39 No 1
P. 7

features in the project area.                   Additionally, the contractor needed to        the walls, which required 1-inch 150-
  The exposed rock along the existing         estimate which sections of the walls could      ksi Williams anchors to be installed to
                                              be constructed with or without shoring.         account for the fluid pressure from the
road was as old as the Ordovician             The preliminary information gave the            stone backfill and any loading from the
Chickamauga Group and Pennsylvanian           contractor some confidence on how the           existing bedded rock.
formation. The exposed rock cut gave a        walls could be constructed, but nothing
good snapshot of the formation of the         was certain. When the walls are bid by the        The area between the back of the panels
sedimentary rocks over the years. The dips    square foot of the wall face, there always      and the rock face was backfilled with free
and faults were evident in the exposed and    is risk in trying to estimate a cost for these  draining no. 57 stone. Building the walls
excavated rock cuts showing the varying       type walls.                                     in this manner sped up construction but
bedding planes, bedding angles and rock       Two Phases of Construction                      did pose some construction issues that
structure.                                                                                    needed to be overcome. Some of the issues
                                                The roadway project was phase-                the contractor had to address were: 1) how
  The coal seams, selective sandstone         constructed in two sections. The first          to install the anchors in the air, and 2)
with coal seams, some of the weathered        project had nine retaining walls, eight         how to keep the post from moving during
shale, and sandstone were the probable        cut walls and one mechanically stabilized       the anchor loading.
cause of the potential for APR that needed    earth (MSE) retaining wall. The total           Methodology Using Free-Stand Posts
to be protected during the excavation         exposed wall surface was 208,846 square
of the material (and properly deposed         feet, and the total wall cost for the first       With the free-stand post, proper
of in a selective deposal site and/or         project was $22.7 million. The second           support was needed to keep the post from
properly encapsulated.) If this material      project had four cut retaining walls. The       moving during the loading of the anchors
was exposed to water, the run-off would       total exposed wall surface was 156,792          along with maintaining the required
be acidic and harmful to the creeks and       square feet, and the total wall cost was        hole opening for the anchors. The area
vegetation.                                   $14.2 million.                                  behind the precast panels was backfilled
                                                                                              with No. 57 stone. The contractor had
  The different rock types encountered          After the project was awarded, the            to develop a means for transferring the
were siltstone, sandy siltstone, sandstone,   contractor did extensive subsurface             load from the pile to the in-place material
shale, interbedded matrix of different        investigation in the location of the            while maintaining the hole for the anchor
rocks, and coal seams. The bedding angles     retaining walls - horizontally and              installation.
varied from lying flat to 90 degrees. The     vertically at the proposed post spacing -
quality of the rock ranged from good          to better define the existing rock line. It       The first method was to form a lean
quality to moderately weathered, to very      was important to know the location of           concrete wedge from the back of the pile
severely weathered. The amount of sandy       competent rock, to determine the method         to the in-place material. The contractor
clay over burden varied throughout the        of construction, number of anchors per          would then drill the hole directly through
limits of the walls.                          post, and the approximate length of             the lean concrete, allowing the concrete
Subsurface Investigations                     anchors.                                        wedge to adequately support the post
                                                                                              during the loading of the anchor. This
  S&ME conducted a subsurface                   This information was used to determine        method provided the needed support but
investigation, but it was limited by the      if the excavation for the wall would be         was very expensive, requiring an extensive
steep terrain and the ability to access       either a complete vertical rock cut, partial    amount of time to install the concrete
the actual wall locations to drill. From      rock cut and soil, or typical top-down          wedges.
the information taken in-field, design        construction. Most of the retaining walls
parameters were determined for the            did allow a vertical or near vertical cut,        Another method was to place 12-
retaining walls, which also were necessary    with a few walls that required the typical      inch PVC pipe at the anchor locations
to estimate the rock line along the wall.     top-down construction with wood                 following the 15-degree inclination of
                                              lagging.                                        the wall anchor. With the pipe properly
  Additional borings were done behind         Retaining Walls Aided Construction              secured on both ends, panels could be
the proposed wall to determine the            Efficiency                                      placed and backfilled with No. 57 stone.
location and quality of the rock for the tie                                                  The PVC pipe provided the hole for the
back anchors. The location of the bedrock       The contractor used galvanized HP             anchor in the stone backfill.
profile information was limited, which        14 x 73 posts with pre-fabricated anchor
created a challenge for the contractor to     tubes, precast concrete panels, and 1-inch        The anchor would be drilled through
determine the rock quantity needed for        150-ksi Williams anchors for the soldier        the PVC pipe to the in-place material
bidding the excavation and the retaining      pile walls. The post spacing varied from        to the required length. The No. 57 stone
walls.                                        eight to 16 feet, depending on the applied      would provide adequate support for the
                                              soil and rock loading and wall geometry.        pile, with the proper sequencing of the
  The rock was estimated by interpolation     These types of retaining walls expedited        anchor loading. This method proved to
and extrapolation from the existing           the construction, speeding efficiency.          be the most effective in both in cost and
borings, and a visual inspection noted                                                        construction time.
the visible exposed rock in the existing        When the rock could be excavated to a         Drill Platforms Utilized
roadway cuts. The amount of overburden        near vertical slope for the retaining wall,
and condition of the rock was estimated to    the post could be installed freestanding          The contractor requested that Neel-
determine estimated post spacing, and the     without the need of wood lagging. The           Schaffer design a drill platform with three
number of anchors and anchor lengths for      rock cuts placed minimum loading on             individual sections that could be adjusted
the cut-retaining walls.
                                                                                      	                                              Continued on page 8

                                                                                              View online at tnpublicworks.com	  7
   2   3   4   5   6   7   8   9   10   11   12