Page 7 - May-June 2021 Vol 39 No 1
P. 7
features in the project area. Additionally, the contractor needed to the walls, which required 1-inch 150-
The exposed rock along the existing estimate which sections of the walls could ksi Williams anchors to be installed to
be constructed with or without shoring. account for the fluid pressure from the
road was as old as the Ordovician The preliminary information gave the stone backfill and any loading from the
Chickamauga Group and Pennsylvanian contractor some confidence on how the existing bedded rock.
formation. The exposed rock cut gave a walls could be constructed, but nothing
good snapshot of the formation of the was certain. When the walls are bid by the The area between the back of the panels
sedimentary rocks over the years. The dips square foot of the wall face, there always and the rock face was backfilled with free
and faults were evident in the exposed and is risk in trying to estimate a cost for these draining no. 57 stone. Building the walls
excavated rock cuts showing the varying type walls. in this manner sped up construction but
bedding planes, bedding angles and rock Two Phases of Construction did pose some construction issues that
structure. needed to be overcome. Some of the issues
The roadway project was phase- the contractor had to address were: 1) how
The coal seams, selective sandstone constructed in two sections. The first to install the anchors in the air, and 2)
with coal seams, some of the weathered project had nine retaining walls, eight how to keep the post from moving during
shale, and sandstone were the probable cut walls and one mechanically stabilized the anchor loading.
cause of the potential for APR that needed earth (MSE) retaining wall. The total Methodology Using Free-Stand Posts
to be protected during the excavation exposed wall surface was 208,846 square
of the material (and properly deposed feet, and the total wall cost for the first With the free-stand post, proper
of in a selective deposal site and/or project was $22.7 million. The second support was needed to keep the post from
properly encapsulated.) If this material project had four cut retaining walls. The moving during the loading of the anchors
was exposed to water, the run-off would total exposed wall surface was 156,792 along with maintaining the required
be acidic and harmful to the creeks and square feet, and the total wall cost was hole opening for the anchors. The area
vegetation. $14.2 million. behind the precast panels was backfilled
with No. 57 stone. The contractor had
The different rock types encountered After the project was awarded, the to develop a means for transferring the
were siltstone, sandy siltstone, sandstone, contractor did extensive subsurface load from the pile to the in-place material
shale, interbedded matrix of different investigation in the location of the while maintaining the hole for the anchor
rocks, and coal seams. The bedding angles retaining walls - horizontally and installation.
varied from lying flat to 90 degrees. The vertically at the proposed post spacing -
quality of the rock ranged from good to better define the existing rock line. It The first method was to form a lean
quality to moderately weathered, to very was important to know the location of concrete wedge from the back of the pile
severely weathered. The amount of sandy competent rock, to determine the method to the in-place material. The contractor
clay over burden varied throughout the of construction, number of anchors per would then drill the hole directly through
limits of the walls. post, and the approximate length of the lean concrete, allowing the concrete
Subsurface Investigations anchors. wedge to adequately support the post
during the loading of the anchor. This
S&ME conducted a subsurface This information was used to determine method provided the needed support but
investigation, but it was limited by the if the excavation for the wall would be was very expensive, requiring an extensive
steep terrain and the ability to access either a complete vertical rock cut, partial amount of time to install the concrete
the actual wall locations to drill. From rock cut and soil, or typical top-down wedges.
the information taken in-field, design construction. Most of the retaining walls
parameters were determined for the did allow a vertical or near vertical cut, Another method was to place 12-
retaining walls, which also were necessary with a few walls that required the typical inch PVC pipe at the anchor locations
to estimate the rock line along the wall. top-down construction with wood following the 15-degree inclination of
lagging. the wall anchor. With the pipe properly
Additional borings were done behind Retaining Walls Aided Construction secured on both ends, panels could be
the proposed wall to determine the Efficiency placed and backfilled with No. 57 stone.
location and quality of the rock for the tie The PVC pipe provided the hole for the
back anchors. The location of the bedrock The contractor used galvanized HP anchor in the stone backfill.
profile information was limited, which 14 x 73 posts with pre-fabricated anchor
created a challenge for the contractor to tubes, precast concrete panels, and 1-inch The anchor would be drilled through
determine the rock quantity needed for 150-ksi Williams anchors for the soldier the PVC pipe to the in-place material
bidding the excavation and the retaining pile walls. The post spacing varied from to the required length. The No. 57 stone
walls. eight to 16 feet, depending on the applied would provide adequate support for the
soil and rock loading and wall geometry. pile, with the proper sequencing of the
The rock was estimated by interpolation These types of retaining walls expedited anchor loading. This method proved to
and extrapolation from the existing the construction, speeding efficiency. be the most effective in both in cost and
borings, and a visual inspection noted construction time.
the visible exposed rock in the existing When the rock could be excavated to a Drill Platforms Utilized
roadway cuts. The amount of overburden near vertical slope for the retaining wall,
and condition of the rock was estimated to the post could be installed freestanding The contractor requested that Neel-
determine estimated post spacing, and the without the need of wood lagging. The Schaffer design a drill platform with three
number of anchors and anchor lengths for rock cuts placed minimum loading on individual sections that could be adjusted
the cut-retaining walls.
Continued on page 8
View online at tnpublicworks.com 7