Page 8 - May-June 2021 Vol 39 No 1
P. 8

LARGE Walls                                  zone to determine which anchor type was       establish bond capacity without reaching
                                             more feasible.                                bedrock. That gave the contractor/
from page 7                                                                                subcontractor the option to use new/
                                               The first anchor installed was a            longer bonding zones rather than
vertically and connected horizontally. That  Williams 150-ksi No. 8 bar. The hole          chasing bedrock. The sacrificial anchors
would allow the contractor to disconnect     was pre-treated with a low mobility           established new bonding length in the
the end section once the anchor had been     grout to stabilize the hole, which utilized   non-rock material.
installed, and move it forward to the        temporary casing. The anchor had a total
opposite end to reconnect the unit to the    length of 50 feet (20-foot free zone and        A new bonding zone of 30 feet was
adjacent platform.                           30-foot bond zone).                           adequate to achieve the design load.
                                                                                           It was GSI’s choice to use permanent
  This process was repeated as the             The low mobility grout was installed        or temporary casing to keep the hole
anchors were installed at this level. This   while the casing was removed and              open. The contractor chose to use the
allowed the drill rig to drive continuously  allowed to cure for 48 hours. The anchor      original 1-inch, 150-ksi rod with the
down the wall as the anchors were            was drilled again and installed. A 20-foot    new 30-foot bonding zone length for
installed. The subcontractor for the         PVC bond breaker was installed for the        the colluvium zone. This section of the
drilling and installation of the anchors     free zone.                                    wall was originally designed for a partial
for the walls for both projects was                                                        rock cut loading but ended up with a full
Colorado-based GeoStabilization                The second sacrificial anchor installed     colluvium soil loading.
International (GSI). GSI was very pleased    used a Z51-mm (two-inch) hollow-bar
with the drill platforms because they        injection anchor (self-drilling). A six-        The area of the colluvium soil was
allowed an uninterrupted method of           inch sacrificial hole was required for the    between pile 15 through pile 25 in Wall
installation of the upper anchors in the     self-drilling anchor. A 50-foot anchor        3. The wall height was around 28.3 feet
retaining walls.                             with a 40-foot bond length and 10-foot        in this area, with a three-anchor section.
                                             free length was used, creating a free zone    The slope behind the wall did not exceed
  Ninety percent of the walls in the rock    challenge for GSI.                            a 2:1 slope.
cuts were installed with the installation
of the freestanding post, cast in place        The anchor used a grout injection             The colluvium soil comprised of a soil
panels, and backfilling without loading      method where the grout was injected           and rock matrix. An estimated loading
the anchors. PVC pipes were used at the      through the hollow stem bar and port          and new bond strength for this type of
anchor locations to maintain the anchor      holes in the sacrificial drill bit. An anti-  material was worked out with the TDOT
hole during backfilling. The 1-inch, 150-    washout additive was added to the grout       geotechnical section. The revised loading
ksi Williams threaded rod anchors were       that congealed when it came in contact        required a higher anchor load of 95 kips.
loaded to 76 kips per anchor from the        with ground water.                            Wall Issues: Under Control
bottom to the top to minimize movement
of the wall.                                   No turbidity or discoloration in the          Another issue that occurred was
                                             water in the Emory River was noticed          maintaining the 15-foot bench between
  In the areas with competent rock, the      after the anchors were installed. The         the walls. This was a huge concern since
installed anchors were loaded to 40 kips     first anchor experienced pull-out failure,    the base of the upper wall was anchored
per anchor and tested with a calibrated      but the self-drilling anchor achieved its     into the rock bench by 30-inch caissons.
torque wrench. The calibration of the        maximum test load without experiencing        The blasting had to be strictly controlled
torque wrench was done by on-site            failure.                                      in order to maintain the integrity of the
testing of in-place anchors. In some of                                                    benches. In some areas where the rock
the areas of Wall 3 on the second project      There were concerns about corrosion,        was severely weathered, rock anchors and
and Wall 4 on the first project, colluvium   so a Z51-mm (two-inch) anchor was             a temporary gunite facing was used to
soil was encountered and caused some         used on a six-inch hole. This anchor was      maintain the stability of the bench until
issues in the anchor installation, with the  galvanized, additional grout cover was        the lower wall was constructed. In some
anchors failing proof testing.               provided, and additional sacrificial steel    areas, wood lagging was used to keep the
                                             in the anchor was incorporated into the       weathered rock from slumping off.
Challenges in Anchoring                      design. The self-drilling anchor was used
  In an area on Wall 4 in project one, GSI   in this area and no further issues were         The lagging secured the weathered rock
                                             encountered.                                  and loose material between the posts. The
had trouble installing and loading the       Working Around Conventional Anchors           HP 14 x 73 post at the 16-foot spacing
anchors between piles 14 and 20 due to                                                     had enough capacity without anchors to
the colluvium material in the area. The        A similar issue occurred in a limited       restrain the No. 57 stone loading before
wall height in this area was around 26.5     area on Wall 3 on the second project,         the anchors were installed.
feet, with a three-anchor section.           where colluvium soils were encountered,       Economical, Efficient Construction
                                             and the conventional anchors were
  The anchors got excessive in length due    failing due to collapsing holes and the         The pre- and post-cast panel
to the colluvium zone, which caused the      inability to get a good bond zone in the      construction provided an economical and
grout to migrate to the stream below. The    colluvium. In order to achieve the design     efficient way of constructing a wall in this
anchor hole advanced through multiple        load, the anchors were advanced until         terrain. The contractor was very pleased
seams of weathered rock and a mixture        competent rock was located, extending         with the construction of the walls, and
of gravel and soil, which made it difficult  the anchors to more than 100 feet in          there were very few issues that had to be
to keep the hole open. GSI installed two     length.                                       addressed during the construction.
sacrificial test anchors in the colluvium
                                               Two sacrificial anchors were used to

8	 TPW May/June 2021
   3   4   5   6   7   8   9   10   11   12   13