Page 8 - May-June 2021 Vol 39 No 1
P. 8
LARGE Walls zone to determine which anchor type was establish bond capacity without reaching
more feasible. bedrock. That gave the contractor/
from page 7 subcontractor the option to use new/
The first anchor installed was a longer bonding zones rather than
vertically and connected horizontally. That Williams 150-ksi No. 8 bar. The hole chasing bedrock. The sacrificial anchors
would allow the contractor to disconnect was pre-treated with a low mobility established new bonding length in the
the end section once the anchor had been grout to stabilize the hole, which utilized non-rock material.
installed, and move it forward to the temporary casing. The anchor had a total
opposite end to reconnect the unit to the length of 50 feet (20-foot free zone and A new bonding zone of 30 feet was
adjacent platform. 30-foot bond zone). adequate to achieve the design load.
It was GSI’s choice to use permanent
This process was repeated as the The low mobility grout was installed or temporary casing to keep the hole
anchors were installed at this level. This while the casing was removed and open. The contractor chose to use the
allowed the drill rig to drive continuously allowed to cure for 48 hours. The anchor original 1-inch, 150-ksi rod with the
down the wall as the anchors were was drilled again and installed. A 20-foot new 30-foot bonding zone length for
installed. The subcontractor for the PVC bond breaker was installed for the the colluvium zone. This section of the
drilling and installation of the anchors free zone. wall was originally designed for a partial
for the walls for both projects was rock cut loading but ended up with a full
Colorado-based GeoStabilization The second sacrificial anchor installed colluvium soil loading.
International (GSI). GSI was very pleased used a Z51-mm (two-inch) hollow-bar
with the drill platforms because they injection anchor (self-drilling). A six- The area of the colluvium soil was
allowed an uninterrupted method of inch sacrificial hole was required for the between pile 15 through pile 25 in Wall
installation of the upper anchors in the self-drilling anchor. A 50-foot anchor 3. The wall height was around 28.3 feet
retaining walls. with a 40-foot bond length and 10-foot in this area, with a three-anchor section.
free length was used, creating a free zone The slope behind the wall did not exceed
Ninety percent of the walls in the rock challenge for GSI. a 2:1 slope.
cuts were installed with the installation
of the freestanding post, cast in place The anchor used a grout injection The colluvium soil comprised of a soil
panels, and backfilling without loading method where the grout was injected and rock matrix. An estimated loading
the anchors. PVC pipes were used at the through the hollow stem bar and port and new bond strength for this type of
anchor locations to maintain the anchor holes in the sacrificial drill bit. An anti- material was worked out with the TDOT
hole during backfilling. The 1-inch, 150- washout additive was added to the grout geotechnical section. The revised loading
ksi Williams threaded rod anchors were that congealed when it came in contact required a higher anchor load of 95 kips.
loaded to 76 kips per anchor from the with ground water. Wall Issues: Under Control
bottom to the top to minimize movement
of the wall. No turbidity or discoloration in the Another issue that occurred was
water in the Emory River was noticed maintaining the 15-foot bench between
In the areas with competent rock, the after the anchors were installed. The the walls. This was a huge concern since
installed anchors were loaded to 40 kips first anchor experienced pull-out failure, the base of the upper wall was anchored
per anchor and tested with a calibrated but the self-drilling anchor achieved its into the rock bench by 30-inch caissons.
torque wrench. The calibration of the maximum test load without experiencing The blasting had to be strictly controlled
torque wrench was done by on-site failure. in order to maintain the integrity of the
testing of in-place anchors. In some of benches. In some areas where the rock
the areas of Wall 3 on the second project There were concerns about corrosion, was severely weathered, rock anchors and
and Wall 4 on the first project, colluvium so a Z51-mm (two-inch) anchor was a temporary gunite facing was used to
soil was encountered and caused some used on a six-inch hole. This anchor was maintain the stability of the bench until
issues in the anchor installation, with the galvanized, additional grout cover was the lower wall was constructed. In some
anchors failing proof testing. provided, and additional sacrificial steel areas, wood lagging was used to keep the
in the anchor was incorporated into the weathered rock from slumping off.
Challenges in Anchoring design. The self-drilling anchor was used
In an area on Wall 4 in project one, GSI in this area and no further issues were The lagging secured the weathered rock
encountered. and loose material between the posts. The
had trouble installing and loading the Working Around Conventional Anchors HP 14 x 73 post at the 16-foot spacing
anchors between piles 14 and 20 due to had enough capacity without anchors to
the colluvium material in the area. The A similar issue occurred in a limited restrain the No. 57 stone loading before
wall height in this area was around 26.5 area on Wall 3 on the second project, the anchors were installed.
feet, with a three-anchor section. where colluvium soils were encountered, Economical, Efficient Construction
and the conventional anchors were
The anchors got excessive in length due failing due to collapsing holes and the The pre- and post-cast panel
to the colluvium zone, which caused the inability to get a good bond zone in the construction provided an economical and
grout to migrate to the stream below. The colluvium. In order to achieve the design efficient way of constructing a wall in this
anchor hole advanced through multiple load, the anchors were advanced until terrain. The contractor was very pleased
seams of weathered rock and a mixture competent rock was located, extending with the construction of the walls, and
of gravel and soil, which made it difficult the anchors to more than 100 feet in there were very few issues that had to be
to keep the hole open. GSI installed two length. addressed during the construction.
sacrificial test anchors in the colluvium
Two sacrificial anchors were used to
8 TPW May/June 2021