Page 11 - May-June2022 Vol 40 No 1
P. 11

cross the road with a ramp system down
         to the building grade.
           Instead of bringing the bridge straight
         into the building, it was determined to
         make the bridge more functional by
         incorporating it into the City’s Greenway
         goals to link their Riverwalk Greenway
         with the Jake Thomas Road Greenway.
           Including the bridge, the project
         would include approximately a half-
         mile of greenway, including 600 feet
         covered by a roof system. The bridge and
         surrounding pedestrian facilities would
         enhance the city’s greenway system by
         providing grade-separate access over
         Teaster Lane, forming an open bicycle
         and pedestrian connection from the
         Riverwalk Greenway across Teaster Lane
         to the Jake Thomas Road corridor.
         Fast-Tracked Project; Compressed
         Schedule
           Due to the compressed schedule,
         the project delivery was broken into
         three phases (each individually bid   logo to brand the two separate lots as   catalyst for economic vitality, according
         and constructed). These included    the River Lot, next to the Little Pigeon   to Earlene Teaster, City Manager of
         mass grading of the parking lot, site   River, and the Mountain Lot. With the   Pigeon Forge.
         construction and construction of the   use of the pervious pavers, the Gresham   “The city is already seeing returns
         pedestrian bridge.                  Smith team continued the branding into   on the parking lot investment,” Teaster
           This process allowed the firm to   the design across the 14-acre parking   said. “Since opening, we have not had
         complete conceptual design and get the   lot with the use of contrasting paver   to close roads, rent parking, or provide
         grading underway while finalizing the   materials. The intent was not only to   transportation. We are saving money
         pedestrian bridge and parking lot design.  create something unique, but also to help  not only on direct expense but also on
           A single bid was obtained for the   define the lot for the high percentage of   manpower to organize and staff auxiliary
         parking lot phase and was $2.5 million   out-of-town visitors.           lots and transit.”
         over the engineer’s estimate, with   New Design: $2 Million Less than     “The parking lot is in the center of
         the stormwater design making up     Original Bid                         the most explosive growth in the city.
         approximately one-third of the total bid.  With infiltration meeting water quality   We are proud to be a catalyst for growth
         Innovative Alternative: Permeable Pavers  requirements, the biofiltration islands   in the Teaster Lane, Jake Thomas Road
           Rising to the budget challenge,   were revised to act as overflow structures   Boulevard area,” she said.
         Gresham Smith worked with the owner   for the pavers and as planting areas. This   Motorists Now Exit Events More Efficiently
         and contractor to choose an alternative   design eliminated more than $2 million   Phil Campbell, General Manager
         design that could reduce total cost of   from the original bid.          of the LeConte Center, said from an
         the project, viewing stormwater design   After finishing the parking lot in   operational standpoint, the event center’s
         as a variable cost. Permeable pavers   December 2020, Gresham Smith      most notable benefit “is the improved
         were chosen as the best solution, which   completed the entire project in April   ingress and egress from the building.”
         combined the costs of the stormwater   2021. Total project budgeted cost was   “Before the new parking facility and
         and parking pavement structure.     $17,152,150, but total project actual   bridge, all of our pedestrian traffic exited
           An open-graded aggregate base     cost was $16,314,615. Now that all three   to the old River Lot. The ability to utilize
         with impermeable berms was          phases of the project are complete, they   entrances on both sides of the building
         designed to replace the detention for   totaled to be approximately $430,000   has essentially cut our large event egress
         the approximately 20-acre site. The   under the contract budgets.        time in half,” Campbell said.
         underground detention was reduced to   A ”Catalyst for Growth”            The project was led by East Tennessee
         a closed system HDPE pipe to perform   Pigeon Forge officials said the 100%   Area Transportation Leader Jason Brady,
         as an underdrain for the large aggregate   city-funded project was critical to the   P.E. and Senior Transportation Engineer
         storage area and overflow relief for the   future success of both LeConte Event   Shap Stiles, P.E. The Gresham Smith
         pavers.                             Center and The Island. In fact, the   team included its transportation market,
           The project’s wayfinding aspects                                       environmental graphics, structures and
         utilized the existing LeConte Center   finished project is being touted as a   utilities groups.


                                                                                        View online at tnpublicworks.com   11
   6   7   8   9   10   11   12   13   14   15   16